If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

An example of someone who would find it important to understand governance in their career is:.
what's was The famous art work made famous by the Romans
Fia needs 3/4 of a cup of brown sugar. She only has a 1/3 cup measuring cup and a 1/8 cup measuring cup. Which should she use and why?
What happened in the Nazi death camps? 1.Prisoners were allowed to earn money for their work 2.Prisoners were tortured and killed 3.Prisoners were "rehabilitate
Who was ready to fight the British in 60 seconds
Show three ways to estimate 3/5 × 91/2
The large portions of the crust which move about on the mantle are the _________________ .
How can the occurrence of fossils and their known age ranges be used to date rocks?
if the template DNA is ATACGT what will the mRNA strand be
• what did darwin observe on the galapagos islands that he thought was the result of evolution?