a contactor hired 150 men to pave a road in 30 days.how many mem will be hire to do the same work in 20 days​

Respuesta :

kevinmario2008 kevinmario2008
  • 05-12-2021

Answer:375

Step-by-step explanation:W = RTN

1 = 1/7500(20)N

1 = 20/7500N

1 = 2/750N

750(1 = 2/750N)

750 = 2N

750/2 = N

375 = N

There are 375 men to do the job in 20 days

Answer Link

Otras preguntas

How could you correctly rewrite the equation 4(10+5)=6(12-2) using the distributive property?
figure WXYZ is shown below. Figure WXYZ is translated up 3 units and 4 units to the right to create WXYZ. What is the measure of angle Z after this transformati
What is the volume of a cylinder with a radius of 7 feet and a height of 12 feet? Use 3.14 for pi. Round your answer to the nearest hundredth. (4 points) 1,846.
Which of the following is an example of a soil conservation method
Which statement describes William lackstone's constribution to government in the United States ?
Best answer gets brainliest!​
Round 6.6 to nearest cent
Rosa is painting two murals.The small mural has an.Area of 2.5 square meters.The Large mural has an area 1.5 times greater than the area of the small mural.What
Read the conclusion about “The Beginnings of the Maasai,” and then answer the question.One purpose of “The Beginnings of the Maasai” is to explain the weather.W
PLEASE HELP SPANISH is this CORRECT or INCORRECT tengo que esperar por el autobus hmu if u can help me with any more