15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Respuesta :

mhanifa
mhanifa mhanifa
  • 04-08-2021

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.

Answer Link
abovejosh
abovejosh abovejosh
  • 04-08-2021
Answer: 10 men explanation: guy above me
Answer Link

Otras preguntas

Plato believed that the soul and body were separate, but would be reunited through reincarnation
how did WWI contribute to the spreading of this flu (influenza 1918)
Which are acceptable names for the plane? Choose all answers that are correct. A. Plane AU B. Plane JAU C. Plane R D. Plane ABC
why did Einstein urge the president to authorize the Manhattan Project
Hi tech was signed in what year
Why are Americans eating more calories today than they did 40 years ago? A.economy has improved. B. Portion sizes and calories counts have increased. C. The g
answer please ir Need help
What is the measure oRCD in the figure below?350
what times what equals 7 but adds to -20
simplify 64 2/3 ÷8 2/3