It take 4 people 40 minutes to clean a garden. How long will it take 6 people to clean the same garden

Respuesta :

loconte loconte
  • 02-07-2021

Answer:

4/9 of an hour (26.666 minutes)

Step-by-step explanation:

4 * x * 40/60 = 1

x * 160/60 = 1

x=60/160 = 6/16 = 3/8 (this is the rate for one worker)

~~~~~~~~~~~~~~~~

6 * (3/8) * x = 1

x = 4/9

Answer Link

Otras preguntas

help with this chemistry problem
Three bags of packing peanuts are used to fill 2 boxes. How many bags of packing peanuts does each box use?
isaac newton's universal law of gravitation
Miranda purchased two pairs of leggings for $2.99 each a bottle of nail polish for $3.49 and a lipstick for $5.99 What was the total cost of her purchase?
When the nurse researcher conducts an electronic literature search, the search yields more than 7000 citations for the topic. the researcher should make which o
which is an example of a social reason for voluntary migration?
"which country in subsaharan africa has spent the last few decades recovering from its former policy of apartheid, or racial separation"
24 loavs of bread cost $48. how much does 10 loaves cost
Identify the adjective in this sentence. His work is getting very sloppy. 1.work 2.getting 3.very 4.sloppy
The process that fuels a star is BEST described as________.