  • 01-04-2021
  • Mathematics
contestada

12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

Tool of thief, toy of queen. Always used to be unseen. Sign of joy, sign of sorrow. Giving all likeness borrowed. What am I? Don't look it up !
Three students divided 53 base ten blocks equally among them.How many base ten blocks does each student receive?How many were left over?
If you need to, and you do not actually have to lie, you can withhold part of the truth from people.
Which expression represents the product of 8 and y?
I need to know the answer and how you got it
Who played the kid who talked really fast in neds diclassified?
Solve for y y/p-q = y/p+q
What are the two qualities that a medicine must possess?
Choose what matches the word The soldiers *gesticulate* as Farquhar reaches the surface of the water. Kneel Shout and swear Shoot Gesture The appearance of the
A class is collecting to recycle.Their goal is to collect 200 ounces of cans the first day3 students each bring in 12.7 ounces of cans,and 4 students each bring