It takes 10 workers 24 hours to do a job.
Fill in the chart.

It takes 10 workers 24 hours to do a job Fill in the chart class=

Respuesta :

biggersis1968p8xgn0 biggersis1968p8xgn0
  • 02-06-2018
5 in 48 
10 in 24
20 in16
30 in12
40 in 8
50 in 4
Answer Link

Otras preguntas

mick paid $2.94 in sales tax on an item that cost $42.00 before tax. At that rate, how much would he pay in sales tax for an item that costs $58.00 before tax?
8 men complete a work in 40 days. How many days will be taken to complete the samed work if 2 more men join them.
Which line from the excerpt contains a metaphor? "I ask them to take a poem" "and hold it up to the light" "like a color slide" "or press an ear against its hi
Why do skeletal muscles work in pairs? A.One tightens and the other relaxes to make the bones move. B.Multiple muscles have to tighten to make joints move.
How is the brain impacted by exercise? Your response should be 8-10 sentences in length.
ellia bought 0.7kg of jelly beans from 1.89 who much 1 kg jelly beans
the number 0.8 can be written as 8/9, so it is a irrational number true or false
What statement is true of Bill Clinton’s presidency? charged with perjury and obstruction of justice experienced a budget surplus through tax cuts and less gove
Solve 7k÷3=21 The solution is k __
Can anyone please tell me the right answer